Project K costs $60,000, it's expected cash inflows are $15,000 per year for 9 years, and it's WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. Project K costs $60,000, it's expected cash inflows are $15,000 per year for 9 years, and it's WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. Project K costs $60,000, it's expected cash inflows are $15,000 per year for 9 years, and it's WACC is 11%. What is the project's NPV? Round your answer to the nearest cent.Explanation / Answer
Year Cash flows PVF@11% Present value 0 $ -60,000 1.000 $ -60,000 1 $ 15,000 0.901 $ 13,514 2 $ 15,000 0.812 $ 12,174 3 $ 15,000 0.731 $ 10,968 4 $ 15,000 0.659 $ 9,881 5 $ 15,000 0.593 $ 8,902 6 $ 15,000 0.535 $ 8,020 7 $ 15,000 0.482 $ 7,225 8 $ 15,000 0.434 $ 6,509 9 $ 15,000 0.391 $ 5,864 Net present value $ 23,056
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.