Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Recall that NPV can be interpreted as the change in the value of the firm at the

ID: 2779588 • Letter: R

Question

Recall that NPV can be interpreted as the change in the value of the firm at the time the project is initiated (t-0). Assume future net benefits increase annually by 5%, the average expected inflation rate over the life of the project, and the nominal MARR is 10%. What is the lesson here? 3. a. Project nominal cash flows and calculate NPV using the nominal MARR. Year Cash Flow ($10,000) 2 0 $4,200 NPV = $ b. Project real cash flows and calculate NPV using the real MARR Year Cash Flow ($10,000)S4,000 0 123 Real MARR = NPV = $ c. What is the lesson (project evaluation best practice)?

Explanation / Answer

1.

Nominal Cash Flows

Year 0: -10000

Year 1: 4200

Year 2: 4200*1.05=4410

Year 3: 4410*1.05=4630.5

So, NPV=-10000+4200/1.1+4410/1.1^2+4630.5/1.1^3=941.77

2.

Real Cash Flows

Year 0: -10000

Year 1: 4200/1.05=4000

Year 2: 4410/1.05^2=4000

Year 3: 4630.5/1.05^3=4000

(1+Nominal MARR)=(1+inflation)*(1+real MARR)

hence, real MARR=1.1/1.05-1=4.7619%

So, NPV=-10000+4000/1.047619+4000/1.047619^2+4000/1.047619^3=941.77

The lesson is that the nominal cash flows should be evaluated suing nominal MARR and real using real MARR and both yield the same result