Recall that NPV can be interpreted as the change in the value of the firm at the
ID: 2779588 • Letter: R
Question
Recall that NPV can be interpreted as the change in the value of the firm at the time the project is initiated (t-0). Assume future net benefits increase annually by 5%, the average expected inflation rate over the life of the project, and the nominal MARR is 10%. What is the lesson here? 3. a. Project nominal cash flows and calculate NPV using the nominal MARR. Year Cash Flow ($10,000) 2 0 $4,200 NPV = $ b. Project real cash flows and calculate NPV using the real MARR Year Cash Flow ($10,000)S4,000 0 123 Real MARR = NPV = $ c. What is the lesson (project evaluation best practice)?Explanation / Answer
1.
Nominal Cash Flows
Year 0: -10000
Year 1: 4200
Year 2: 4200*1.05=4410
Year 3: 4410*1.05=4630.5
So, NPV=-10000+4200/1.1+4410/1.1^2+4630.5/1.1^3=941.77
2.
Real Cash Flows
Year 0: -10000
Year 1: 4200/1.05=4000
Year 2: 4410/1.05^2=4000
Year 3: 4630.5/1.05^3=4000
(1+Nominal MARR)=(1+inflation)*(1+real MARR)
hence, real MARR=1.1/1.05-1=4.7619%
So, NPV=-10000+4000/1.047619+4000/1.047619^2+4000/1.047619^3=941.77
The lesson is that the nominal cash flows should be evaluated suing nominal MARR and real using real MARR and both yield the same result
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.