Homework 5: Adjusting for project risk 2 (Q) Kindercare is considering a project
ID: 2785592 • Letter: H
Question
Homework 5: Adjusting for project risk 2 (Q) Kindercare is considering a project that will result in initial aftertax cash savings of $3.5 million at the end of the first year, and these savings will grow at a rate of 4 percent per year indefinitely. The firm has a target debt-equity ratio of .55, a cost of equity of 13 percent, and an aftertax cost of debt of 5.5 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm undertakes; management uses the subjective approach and applies an adjustment factor of +2 percent to the cost of capital for such risky projects. Under what circumstances should Kindercare take on the project?Explanation / Answer
D/E=0.55
proportion of debt, D/(D+E)=1/(1+1/0.55)=0.354839
proportion of equity=1-proportion of debt=1-0.354839=0.645161
Cost of capital=0.354839*5.5%+0.645161*13%=10.3387%
Project's cost of capital=10.3387%+2%=12.3387%
NPV=-Initial Investment+3.5/1.123387+3.5*1.04/1.123387
=-Initial Investment+3.5/(0.23387-0.04)
=-Initial Investment+18.05333
So, project should be undertaken when NPV>0
Hence, -Initial Investment+18.05333>0
Initial Investment<18.0533
So, the initial inevstment for the project must be less than 18.0533 milion for the project to be undertaken
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.