To solve the bid price problem presented in the text, we set the project NPV equ
ID: 2792807 • Letter: T
Question
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems. Romo Enterprises needs someone to supply it with 122,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $890,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that, in five years, this equipment can be salvaged for $72,000. Your fixed production costs will be $327,000 per year, and your variable production costs should be $10.50 per carton. You also need an initial investment in net working capital of $77,000. Assume your tax rate is 34 percent and you require a 10 percent return on your investment.
a. Assuming that the price per carton is $17.20, what is the NPV of this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
NPV $
b. Assuming that the price per carton is $17.20, find the quantity of cartons per year you need to supply to break even. (Do not round intermediate calculations and round your answer to nearest whole number.)
Quantity of cartons
c. Assuming that the price per carton is $17.20, find the highest level of fixed costs you could afford each year and still break even. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
Fixed cost:
Explanation / Answer
Initial outlay = FCinv + WCinv
Here the cost of equipment is $890,000 and net working capital will increase by $77,000
Thus,
Initial outlay = FCinv + WCinv
=890000+77000
=967000
Depreciation is based on SLM with salvage value of 72000 in 5 years
Thus depreciation per year = 890000-72000 / 5 = 163600
Sales = price per carton * no of carton = 17.20*122000 = 2098400
varibale cosst = varibal cost per carton * no of carton = 10.50*122000 = 1281000
Fixed cost = 327000 and tax = 34%
After tax operating cash flow = (sales-cost-depreciation)*(1-tax)+depreciation
=(2098400-1281000-327000-163600)*(1-0.34) + 163600
=326800*0.66 + 163600
=379288
Terminal year cashflow = salvage + WCinv - Tax*(salvage-book value)
=72000+77000 - 0.34*(72000-0)
=149000 - 24480
=124520
(and this will get added to final year ie year 5 cashflow and it will be 124520+379288=503808)
Answer a. NPV calculation at 10% cost of investment is as below:
Years
Cashflow
0
-967000
1
379288
2
379288
3
379288
4
379288
5
503808
NPV at 10%
$571,343.17
answer b. The fixed cost per year = 327000
and sales - variable cost = 17.20 - 10.50 = 6.7
And thus breakeven cartons needed per year = 327000 / 7.7 = 48806
answer c. Sales = price per carton * no of carton = 17.20*122000 = 2098400
varibale cosst = varibal cost per carton * no of carton = 10.50*122000 = 1281000
Thus the highest level of fixed cost that can be afforded = 2098400 - 1281000 = 817400 per year.
Years
Cashflow
0
-967000
1
379288
2
379288
3
379288
4
379288
5
503808
NPV at 10%
$571,343.17
You can also calculate NPV in your financial calculator by inserting all the respective cashflows and by pressing CPT and then NPV at 10%Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.