Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for

ID: 2797701 • Letter: C

Question

CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 4 Project M-$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N $54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations Project M Project N Calculate MIRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations Project M Project N Calculate payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations Project M Project N years years Calculate discounted payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations Project M Project N years years b. Assuming the projects are independent, which one(s) would you recommend? c. If the projects are mutually exclusive, which would you recommend? d. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR? Select Select Select

Explanation / Answer

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-18000

-18000

-18000

-18000

1

6000

-12000

5263

-12737

2

6000

-6000

4617

-8120

3

6000

0

4050

-4070

4

6000

6000

3552

-518

5

6000

12000

3116

2598

NPV at 14%

$2,279.37

IRR

19.86%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

19.86%

Payback period = 2+(6000-0)/6000

3.000

Discounted Payback period = 4+(3116-2598)/3116

4.166

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-54000

-54000

-54000

-54000

1

16800

-37200

14737

-39263

2

16800

-20400

12927

-26336

3

16800

-3600

11340

-14997

4

16800

13200

9947

-5050

5

16800

30000

8725

3676

NPV at 14%

$3,224.35

IRR

16.80%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

16.80%

Payback period = 3+(16800-13200)/16800

3.214

Discounted Payback period = 4+(8725-3676)/8725

4.579

For Project M:

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-18000

-18000

-18000

-18000

1

6000

-12000

5263

-12737

2

6000

-6000

4617

-8120

3

6000

0

4050

-4070

4

6000

6000

3552

-518

5

6000

12000

3116

2598

NPV at 14%

$2,279.37

IRR

19.86%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

19.86%

Payback period = 2+(6000-0)/6000

3.000

Discounted Payback period = 4+(3116-2598)/3116

4.166

For Project N:

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-54000

-54000

-54000

-54000

1

16800

-37200

14737

-39263

2

16800

-20400

12927

-26336

3

16800

-3600

11340

-14997

4

16800

13200

9947

-5050

5

16800

30000

8725

3676

NPV at 14%

$3,224.35

IRR

16.80%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

16.80%

Payback period = 3+(16800-13200)/16800

3.214

Discounted Payback period = 4+(8725-3676)/8725

4.579

Answer a.

NPV for Project M = $2279.37

NPV for Project N = $3224.35

IRR for Project M = 19.86%

IRR for Project N = 16.80%

MIRR for Project M = 19.86%

MIRR for Project N = 16.80%

Payback period for Project M = 3 years

Payback period for Project N = 3.214 years

Discounted Payback period for Project M = 4.166 years

Discounted Payback period for Project N = 4.579 years

Answer b.

Assuming the project are independent, both the Project M and Project N should be accepted.

Answer c.

If the projects are mutually exclusive, Project N should be selected as it has higher NPV among the two.

Answer d.

The decision to accept project depends on NPV and doesnt stand on IRR and thus IRR greater than WACC should be accepted which is true in this case for both the projects.

Based on the details given please see the schedule below for NPV, IRR, MIRR, Payback period and discounted payback period:
For Project M:

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-18000

-18000

-18000

-18000

1

6000

-12000

5263

-12737

2

6000

-6000

4617

-8120

3

6000

0

4050

-4070

4

6000

6000

3552

-518

5

6000

12000

3116

2598

NPV at 14%

$2,279.37

IRR

19.86%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

19.86%

Payback period = 2+(6000-0)/6000

3.000

Discounted Payback period = 4+(3116-2598)/3116

4.166


For Project N:

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-54000

-54000

-54000

-54000

1

16800

-37200

14737

-39263

2

16800

-20400

12927

-26336

3

16800

-3600

11340

-14997

4

16800

13200

9947

-5050

5

16800

30000

8725

3676

NPV at 14%

$3,224.35

IRR

16.80%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

16.80%

Payback period = 3+(16800-13200)/16800

3.214

Discounted Payback period = 4+(8725-3676)/8725

4.579


Answer a.
NPV for Project M = $2279.37
NPV for Project N = $3224.35
IRR for Project M = 19.86%
IRR for Project N = 16.80%
MIRR for Project M = 19.86%
MIRR for Project N = 16.80%
Payback period for Project M = 3 years
Payback period for Project N = 3.214 years
Discounted Payback period for Project M = 4.166 years
Discounted Payback period for Project N = 4.579 years

Answer b.
Assuming the project are independent, both the Project M and Project N should be accepted.

Answer c.
If the projects are mutually exclusive, Project N should be selected as it has higher NPV among the two.

Answer d.
The decision to accept project depends on NPV and doesnt stand on IRR and thus IRR greater than WACC should be accepted which is true in this case for both the projects.

Based on the details given please see the schedule below for NPV, IRR, MIRR, Payback period and discounted payback period:

For Project M:

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-18000

-18000

-18000

-18000

1

6000

-12000

5263

-12737

2

6000

-6000

4617

-8120

3

6000

0

4050

-4070

4

6000

6000

3552

-518

5

6000

12000

3116

2598

NPV at 14%

$2,279.37

IRR

19.86%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

19.86%

Payback period = 2+(6000-0)/6000

3.000

Discounted Payback period = 4+(3116-2598)/3116

4.166

For Project N:

Project N

Cumulative Cashflow = Cumulative cashflow of previous year + Cashflow of current year

Discounted Cashflow = Cashflow / 1+14^n

Discounted Cumulative Cashflow = Discounted Cumulative cashflow of previous year + Discounted Cashflow of current year

Years

Project N Cashflow

Cumulative Cashflow

Discounted Cashflow

Discounted Cumulative Cashflow

0

-54000

-54000

-54000

-54000

1

16800

-37200

14737

-39263

2

16800

-20400

12927

-26336

3

16800

-3600

11340

-14997

4

16800

13200

9947

-5050

5

16800

30000

8725

3676

NPV at 14%

$3,224.35

IRR

16.80%

MIRR assuming finance rate as WACC and reinvestment rate as IRR

16.80%

Payback period = 3+(16800-13200)/16800

3.214

Discounted Payback period = 4+(8725-3676)/8725

4.579

Answer a.

NPV for Project M = $2279.37

NPV for Project N = $3224.35

IRR for Project M = 19.86%

IRR for Project N = 16.80%

MIRR for Project M = 19.86%

MIRR for Project N = 16.80%

Payback period for Project M = 3 years

Payback period for Project N = 3.214 years

Discounted Payback period for Project M = 4.166 years

Discounted Payback period for Project N = 4.579 years

Answer b.

Assuming the project are independent, both the Project M and Project N should be accepted.

Answer c.

If the projects are mutually exclusive, Project N should be selected as it has higher NPV among the two.

Answer d.

The decision to accept project depends on NPV and doesnt stand on IRR and thus IRR greater than WACC should be accepted which is true in this case for both the projects.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote