8. You have calculated an investment to have an NPV of $1. Do you ACCEPT or REJE
ID: 2800485 • Letter: 8
Question
8. You have calculated an investment to have an NPV of $1. Do you ACCEPT or REJECT this project, given no further information. Assume you are satisfied with the expected payback of the project.
9. Risk free rate: 2.3%
Beta: 1.8
Equity risk premium: 7.5%
D/E: 0.8
Cost of debt (pretax): 5.5%
Corporate tax rate: 27%
Initial investment (CF at year 0): 47,000
Cash flow at end of year 1: 17,500
Cash flow at end of year 2: 19,900
Cash flow at end of year 3: 20,650
[No more cash flows.]
FIND: NPV
[HINT: First, find WACC. Then, use this as the discount rate to find the present value of future cash flows. Then subtract initial cost to find NPV....]
10.If your firm has a current ratio less than 1.0, then what must be true:
a. D/E must also be less than 1.0
b. Profit margin cannot be positive
c. Profit margin must be positive
d. Working capital must be negative
Explanation / Answer
8)
Net present value (NPV) = Present value of cash inflows-Present value of cash outflows.
If a project has positive NPV, firm should accept the project and vice-versa. A project with positive NPV will increase firm value. Here, NPV is $1. So project should be accepted.
Accept the project.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.