Time Period 0 1 2 3 4 Project A Cash Flow (1,000) 450 450 450 450 Project B Cash
ID: 2803469 • Letter: T
Question
Time Period
0
1
2
3
4
Project A Cash Flow
(1,000)
450
450
450
450
Project B Cash Flow
(1,000)
0
0
0
2,000
Cost of capital 13%
1. Compute the NPV of project A (round answer to nearest dollar)
2. Compute the NPV of project B (round answer to nearest dollar)
3. Compute the IRR of project A (give answer as XX.XX%)
4. Compute the IRR of project B (give answer as XX.XX%)
5. Compute the MIRR of project A (give answer as XX.XX%)
6. Compute the MIRR of project B (give answer as XX.XX%)
7. Which project would you take if they were mutually exclusive?
8. Which project would you take if they were independent?
Time Period
0
1
2
3
4
Project A Cash Flow
(1,000)
450
450
450
450
Project B Cash Flow
(1,000)
0
0
0
2,000
Explanation / Answer
1. NPV = Present Value of Cash Inflows - Present Value of Cash Outflows
= $ 450 * 1/(1.13) ^ 1 + $ 450 * 1/(1.13) ^ 2 + $ 450 * 1/(1.13) ^ 3 +$ 450 * 1/(1.13) ^ 4 - $ 1,000
= $ 1,338.51 - $ 1,000
= $ 338.51
2.
NPV = Present Value of Cash Inflows - Present Value of Cash Outflows
= $2,000 * 1/(1.13) ^ 4 - $ 1,000
= $ 1,226.64- $ 1,000
= $ 226.64
3.
Let the IRR be x.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
1,000=450/(1.0x) +450/ (1.0x)^2 +450 /(1.0x)^3 +450 /(1.0x)^ 4
Or x= 28.50%
Hence the IRR is 28.50%
4.
Let the IRR be x.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
1,000=0/(1.0x) +0/ (1.0x)^2 +0 /(1.0x)^3 +2,000 /(1.0x)^ 4
Or x= 18.92%
Hence the IRR is 18.92%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.