Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider a project to supply Detroit with 25,000 tons of machine screws annually

ID: 2804651 • Letter: C

Question

Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,600,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $650,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value of $600,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $290 per ton. The engineering department estimates you will need an initial net working capital investment of $260,000. You require a return of 12 percent and face a marginal tax rate of 38 percent on this project.

  

What is the estimated OCF for this project? (Do not round intermediate calculations. Enter your answer in whole dollars, not millions of dollars, e.g., 1,234,567.)

  

  

What is the estimated NPV for this project? (Enter your answer in dollars, not millions of dollars, e.g., 1,234,567. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What is the worst-case NPV for this project? The best-case NPV? (A negative answer should be indicated by a minus sign. Enter your answer in dollars, not millions of dollars, e.g., 1,234,567. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,600,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $650,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value of $600,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $290 per ton. The engineering department estimates you will need an initial net working capital investment of $260,000. You require a return of 12 percent and face a marginal tax rate of 38 percent on this project.

Explanation / Answer

Given, fixed cost = 2,600,000 and working capital requirement = 260,000
Initial outlay = FCinv + WCinv
= 2600,000+260,000
=2860,000

The asset will depreciate on SLM basis to zero over 5 years
thus depreciation per year = 2600,000 / 5 = 520,000

Terminal value = Salvage + WCinv - tax*(salvage-bookvalue)
=600,000+260,000 - 0.38*(600,000-0)
=860,000 - 228000
=632,000

Answer a-1.
Sales = Price*units = 290*25000 = 7250,000
Variable cost = 200*25000 = 5000,000
Fixed cost = 650,000
Total cost = 5000,000+650,000 = 5650,000

OCF = sales-cost-depreciation*(1-tax) + Depreciation
=(7250,000-5650,000-520,000)*(1-0.38) + 520,000
=1189600

Answer a-2.
NPV at 12% required return is:

Year

Cashflow

0

-2860000

1

1189600

2

1189600

3

1189600

4

1189600

5

1821600

NPV at 12%

$1,595,406.73


Given, the initial cost can be in the range of +-15% thus fixed cost = 2,600,000
Hence worst case FCinv = 2600,000*(1-0.15) = 2210,000
Best case FCinv = 2600,000*(1+0.15) = 2990,000
and,
the net working capital can be in the range of +-5% thus working capital = 260,000
Hence worst case WCinv = 260,000*(1-0.05) = 247,000
Best case WCinv = 260,000*(1+0.05) = 273,000

Worst case Initial outlay = FCinv + WCinv
= 2210,000+247,000
= 2457,000

Best case Initial outlay = FCinv + WCinv
= 2990,000+273,000
= 3263,000


Salvage value is +-15% thus salvage = 600,000
Worst case salvage value = 600,000*(1-0.15) = 510,000
Best case salvage value = 600,000*(1+0.15) = 690,000

Thus worst case terminal cashflow = 510,000+247,000 - 0.38*(510,000-0)
= 757,000 - 193800
= 563200

Best case terminal cashflow = 690,000+273,000 - 0.38*(690,000-0)
=963000 - 262,200
=700,800


The sales price for can be in the range of +-10%
thus worst case Sales = Price*units = 290*(1-0.10)*25000 = 6525,000
best case sales = Price*units = 290*(1+0.10)*25000 = 7975,000
Variable cost = 200*25000 = 5000,000
Fixed cost = 650,000
Total cost = 5000,000+650,000 = 5650,000

Worst case OCF = sales-cost-depreciation*(1-tax) + Depreciation
=(6525,000-5650,000-520,000)*(1-0.38) + 520,000
=740,100

Best case OCF = sales-cost-depreciation*(1-tax) + Depreciation
=(7975,000-5650,000-520,000)*(1-0.38) + 520,000
=1639100

Best and worst case NPV at 12% is:

Year

Worst case

Best case

0

-2457000

-3263000

1

740100

1639100

2

740100

1639100

3

740100

1639100

4

740100

1639100

5

1276300

2339900

NPV at 12%

$459,954.60

$2,717,179.83


Year

Cashflow

0

-2860000

1

1189600

2

1189600

3

1189600

4

1189600

5

1821600

NPV at 12%

$1,595,406.73

You can also find NPV by inserting respective cashflows in the financial calculator and pressing CPT NPV at 12%
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote