Assume you are risk-averse and have the following three choices. Expected Standa

ID: 2822284 • Letter: A

Question

Assume you are risk-averse and have the following three choices.    

           

                  Expected                                 Standard

                     Value                                    Deviation         

A         $          2,010 $          1,700

B                    2,420 1340

C                    2,180 1,490             

   

Compute the coefficient of variation for each. (Round your answers to 3 decimal places.)

Coefficient of Variation

A _______

B_______

C_______

Which project will you select? Project A   Project B   or Project C ?

Explanation / Answer

coefficient of variation=Standard deviation/Expected value

Hence since individual is risk averse;choice having lowest  coefficient of variation must be selected ie Project B.

coefficient of variation A (1700/2010)=0.846 B (1340/2420)=0.554 C (1490/2180)=0.683(Approx).