Assignment: Module 5 Homework Asspnen Score 0.00% Save Submit Assignment for Gra

ID: 2824541 • Letter: A

Question

Assignment: Module 5 Homework Asspnen Score 0.00% Save Submit Assignment for Grading Question 16 of 20 Questions Problem 11.11 14. 15 O 16 Check My Work (3 remaining) o Click here to read the eBook: Net Present Value (NPV) CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $11,000 and its expected cash flows would be $6,500 per year for 5 years. 18 O Mutually exclusive Project L costs $48,000 and its expected cash flows would be $12,400 0 per year for 5 years. If both projects have a WACC of 13%, which project would you 19. Select the correct answer. ?aNether Projct S nor L, since each projects NPV ?. ?.Projet L, since the NPL > NPVS- d. Project S, since the NPVs > NPVL e.Both Projects S and L, since both projects have IRR's > 0. Check My Work (3 remaining) 2 4

Explanation / Answer

Answer : "d. Project S, since the NPV(S) >NPV(L)" => NPV PROJ S = CASH INFLOW * PVIFA(COST%,N) - INITIAL CASH OUTFLOW NPV PROJ S = 6500 * PVIFA(13%,5) - 11000 6500*3.517 - 11000 = 11860.50 NPV PROJ L = 12400 * PVIFA(13%,5) - 48000 12400*3.517 - 48000 = -4389.20

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote