Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

You have just started your summer? internship, and your boss asks you to review

ID: 2824657 • Letter: Y

Question

You have just started your summer? internship, and your boss asks you to review a recent analysis that was done to compare three alternative proposals to enhance the? firm's manufacturing facility. You find that the prior analysis ranked the proposals according to their? IRR, and recommended the highest IRR? option, Proposal A. You are concerned and decide to redo the analysis using NPV to determine whether this recommendation was appropriate. But while you are confident the IRRs were computed? correctly, it seems that some of the underlying data regarding the cash flows that were estimated for each proposal was not included in the report. For Proposal? B, you cannot find information regarding the total initial investment that was required in Year 0. And for Proposal? C, you cannot find the data regarding additional salvage value that will be recovered in Year 3. Here is the information you have? (in $? millions):

Proposal

IRR

Year 0

Year 1

Year 2

Year 3

A

60.0 %

negative $ 100

$ 30

$ 153

$ 88

B

57.3 %

question mark?

$ 0

$ 206

$ 95

C

55.8 %55.8%

negative $ 100

$ 37

$ 0

$204+?

a. Fill in the missing values.

b. Suppose the appropriate cost of capital for each alternative is

10 %

Using this? information, determine the NPV of each proposal. Which project should the firm?choose?

c. Can the IRR rule be used in this? situation? Justify.

Proposal

IRR

Year 0

Year 1

Year 2

Year 3

A

60.0 %

negative $ 100

$ 30

$ 153

$ 88

B

57.3 %

question mark?

$ 0

$ 206

$ 95

C

55.8 %55.8%

negative $ 100

$ 37

$ 0

$204+?

Explanation / Answer

IRR is the rate of return that makes initial investment equla to present value of cash inflows

a)

Proposal B:

Initial investment = 0 + 206 / ( 1 + 0.573)2 + 95 / ( 1 + 0.573)3

Initial investment = 0 + 83.254895 + 24.408295

Initial investment = $107.67

Proposal C:

100 = 37 / ( 1 + 0.558) + 0 + 204 / ( 1 + 0.558)3 + X / ( 1 + 0.558)3

100 = 23.748395 + 0 + 53.942095 + X/ 3.781833

22.30951 = X/ 3.781833

X = 84.3708

Salvage value is $84.307

b)

NPV = Present value of cash inflows - present value of cash outflows

NPV of project A = -100 + 30 / ( 1 + 0.1)1 + 153 / ( 1 + 0.1)2 + 88 / ( 1 + 0.1)3

NPV of project A = $119.8347

NPV of project B = -107.67+ 0 + 206 / ( 1 + 0.1)2 + 95 / ( 1 + 0.1)3

NPV of project B = $133.953

NPV of project C = -100 + 37 / ( 1 + 0.1)1 + 0 + 204 / ( 1 + 0.1)3 + 84.307 / ( 1 + 0.1)3

NPV of project C = $150.294

As per NPV method, we should choose project C as it has the highest NPV.

c)

When the projects are mutually exclusive projects, we always go by the NPV rule.

NPV of project C = $133.953

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote