In a project analysis using three time estimates with more than one critical pat
ID: 2908730 • Letter: I
Question
In a project analysis using three time estimates with more than one critical path existing, how does the project manager decide which variances to use in arriving at the probability of meeting the project due date?
The project manager averages the variances and uses that
The project manager uses the smallest variance in order to get the highest probability of on-time completion
The project manager uses the variances considered most correct
The project manager uses the largest variances in order to understate the probability of on-time completion
The project manager uses the most likely estimate plus the amount of slack time in the project.
Explanation / Answer
The 4th option is correct.
The project manager uses the largest variances in order to understate the probability of on-time completion.