33. Find the C pk index for a process with USL = 550, LSL = 540, m = 543, and s

ID: 2917066 • Letter: 3

Question

33. Find the Cpkindex for a process with USL = 550, LSL = 540,m = 543, and s= 0.75.

A) 1.33

B) 2.22

C) 1.25

D) 1.75

34. Statistical process control chartsmeasure

A) the quality of a product.

B) the stability of the processdistribution.

C) the capability of a process.

D) more than one of the above.

35. In statistical process control,overadjustment of a process results in making

A) a Type I error.

B) a Type II error.

C) both a Type I and Type II error.

D) neither a Type I nor Type IIerror.


45. Which does the first letter mean inthe Six-Sigma DMAIC acronym?

A) Design

B) Distribute

C) Describe

D) Define

A) In control.

B) Out of control with respect to X-bar, incontrol with respect to R.

C) In control with respect to X-bar, out ofcontrol with respect to R.

D) Out of control with respect to both X-bar andR.

Explanation / Answer

c)1.25 is the process capability ratio d) More than one of the above a) A Type I error d) Define is the correct answer a) Incontrol