A lead inspector at ElectroTech, an electronics assembly shop, wants to convince management that it takes longer, on a per-component basis, to inspect large devices with many components than it does to inspect small devices because it is difficult to keep track of which components have already been inspected. To prove her point, she has collected data from the last 25 devices. The data are shown in the accompanying table Number of Components on Device Inspection Time (seconds) 13 30 15 51 24 42 12 19 42 63 26 80 30 12 31 19 52 60 72 102 59 19 25 16 13 21 12 23 67 70 a. A scatterplot of the above data is shown below. Does the lead inspector's claim seem credible? Yes O No b-1. Estimate the linear, quadratic, and cubic regression models. Report the Adjusted R2 for each model. (Round your answers to 4 decimal places.) usted R2 Linear model Quadratic model Cubic model b-2. Which model has the best fit? Linear model O Quadratic model O Cubic model c. Use the best model to predict the time required to inspect a device with 35 components. (Round your answer to 2 decimal places.) Time requiredExplanation / Answer
Answer to each part of the question below:
a-1. Yes
b-1. The models are estimated in the respective figures. Adj Rsquares are in the respective diagrams.
b-2
The best fit is the fit with highest polynomials. i.e. cubic model.
c. A device with 35 components takes :
= 0.0023*35^3 - 0.2068*35^2 + 7.5627*35 - 21.848 seconds
= 88.13 seconds
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.