You work for Zulu Corporation. They make safety equipment for race car drivers.
ID: 2930076 • Letter: Y
Question
You work for Zulu Corporation. They make safety equipment for race car drivers. You have been assigned the design for a new latch mechanism for the 5-point seat harness. In the past, the latch mechanism securely held the driver in place, but was very expensive to manufacture. The requirements for the new latch mechanism include a 50% reduction in its cost. You have been asked to estimate how long it will take to redesign the mechanism using the weighted-average method to the 99.7% confidence interval. You have been given three estimates by your team members:
Optimistic: 8 weeks
Pessimistic: 35 weeks
Expected: 25 weeks.
Provide the following values rounded to the nearest integer:
Mean:
Standard Deviation:
Final value at 99.7% confidence interval:
Explanation / Answer
Let write pessimistic - p, Expected -e and optimisitc - o
so mean value of project time = (o + 4e + p)/6 = (8 + 4 * 25 + 35)/6 = 23.83 weeks
Standard deviation of project time = (p -o)/6 = (35 - 8)/6 = 4.5 weeks
99.7% confidence interval means 3 standard deviation away from mean.
Final value at 99.7% confidence interval = Mean + 3 * standard deviation = 23.83 + 3 * 4.5 = 37.33 weeks
so, it will take 37.33 weeks for 99.7% confidence interval.