3) A small town at risk of periodic flooding is considering the option of buildi
ID: 3013022 • Letter: 3
Question
3) A small town at risk of periodic flooding is considering the option of building a levee to reduce flood risk. When a flood occurs, the average cost of damages is $300,000. The following tables provide information on the frequency of different floods and the cost of building levees of different heights. Assuming that a levee lasts 50 years and a MARR of 12%, should a levee be built? And if so, how high?
Flood Height Above River Bank (m)
Flood Frequency
2
Once every 3 years
2.5
Once every 8 years
3
Once every 25 years
3.5
Once every 50 years
4
Once every 100 years
Levee Height (m)
Cost
2
$100,000
2.5
$165,000
3
$300,000
3.5
$400,000
4
$550,000
Flood Height Above River Bank (m)
Flood Frequency
2
Once every 3 years
2.5
Once every 8 years
3
Once every 25 years
3.5
Once every 50 years
4
Once every 100 years
Explanation / Answer
Here we calculate the Net Present Value of all the damages saved by Levee during 50 years for period for all type of flood levels using the formula:
NPV= -Initial investment + [(Cash Inflow1)/(1+r)1] + [(Cash Inflow2)/(1+r)2] + [(Cash Inflow3)/(1+r)3]…..+ [(Cash Inflown)/(1+r)n]
We will select that levee which has highest NPV.
Calculation for 2 Meters:
NPV = -$100,000 + ($300,000/1.123) + ($300,000/1.126) + ($300,000/1.129) + ($300,000/1.1212) + ($300,000/1.1215) + ($300,000/1.1218) + ($300,000/1.1221) + ($300,000/1.1224) + ($300,000/1.1227) + ($300,000/1.1230) + ($300,000/1.1233) + ($300,000/1.1236) + ($300,000/1.1239) + ($300,000/1.1242) + ($300,000/1.1245) + ($300,000/1.1248) = $637,656.73
Calculation for 2.5 Meters:
NPV = -$165,000 + ($300,000/1.128) + ($300,000/1.1216) + ($300,000/1.1224) + ($300,000/1.1232) + ($300,000/1.1240) + ($300,000/1.1248) = -$83,790.09
Calculation for 3 Meters:
NPV = -$300,000 + ($300,000/1.1225) + ($300,000/1.1250) = -$281,314.95
Calculation for 3.5 Meters:
NPV = -$400,000 + ($300,000/1.1250) = -$398,961.95
Calculation for 4 Meters:
NPV = - [($550,000) + ($550,000/1.1251)] + ($300,000/1.12100) = -$551,695.60
We see that highest value is $637,656.73 which belongs to 2 meter Hence we will build 2 meter levee.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.