Question
Use the following scenario and data for the questions Doug Casey tva charge ofplanning and coordinating text quarter's sales management Doug listed the following actnty formation for das proyect . anmg program for his company Estimated Time ActivityoDescription Plan nvite C List meeting Da Select locationa Co travel B. Da Make final check with Go Prepare and mail brochureo Go Ho Take reservations | Handle last minute detailp Before answering the following questions, you may want to schedule the project by determining the earliest start time, earliest finish time, latest start time, and latest finish time for each activity, and to compute the slack time for each activity You may use the following table Activityo ImmediaeEmated Time Eliest Earliest Latest Latest Slack B, DoExplanation / Answer
Duration ES EF LS LF Slack A 3 0 3 1 4 1 B 3 3 6 4 7 1 C 3 0 3 0 3 0 D 4 3 7 3 7 0 E 2 7 9 8 10 1 F 2 9 11 10 12 1 G 2 7 9 7 9 0 H 3 9 12 9 12 0 I 2 12 14 12 14 0 6) (9,11) 7) 0 8) 1 9) C,D,G,H,I Activities with zero slack
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.