Please provide explanations for the answers below. Thank you!

81. In a P-chart the size of the sampel can vary.

True or False

82. When N>25, there is no need for a shortcut formula to determine the upper and lower control limits for an X-Bar chart.

True or False

83. When N<12, the range is used as an estimate for the standard deviation when constructing an X-bar chart.

True or False

84. An alpha or type I error occurs when a sample mean exceeds the LCL or LCL but the process is still in control

True or False

85. When a six sigma standard is used to design a process, the number of defects per million outcomes will be___

a.) 6219

b.) 320

c.) 3.4

d.) 6

Explanation / Answer

81. In a P-chart the size of the sampel can vary. True

82. When N>25, there is no need for a shortcut formula to determine the upper and lower control limits for an X-Bar chart. True

83. When N<12, the range is used as an estimate for the standard deviation when constructing an X-bar chart. True

84. An alpha or type I error occurs when a sample mean exceeds the LCL or LCL but the process is still in control

True

85. When a six sigma standard is used to design a process, the number of defects per million outcomes will be___

correct answer: c.) 3.4