Similar Tests - Assembly Time: You manufacture boxed swing sets and want to conv
ID: 3066805 • Letter: S
Question
Similar Tests - Assembly Time: You manufacture boxed swing sets and want to convince customers that it takes less than 2 hours to assemble one. You take a sample of adults, have them assemble the swing sets, and time them. About 78% of the adults get done in just under 2 hours but the other 22% take much more than 2 hours. You are considering the two claims given below. For each claim, choose the appropriate alternate hypothesis for the test.
(a) You claim that most adults take less than 2 hours to assemble the swing set.
H1: p < 2
H1: p > 0.5
H1: x < 2
H1: ? < 2
(b) You claim that the average assembly time is less than 2 hours.
H1: ? < 2
H1: p < 2
H1: x < 2
H1: p > 0.5
Explanation / Answer
a) as this hypothesis is about proportion of people who take less than 2 Hours
therefore alternate hypothesis:
H1: p > 0.5
b) for this is about average value
therefore alternate hypothesis:
H1: ? < 2