Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following estimates of activity times (in days) are available for a small pr

ID: 3111372 • Letter: T

Question

The following estimates of activity times (in days) are available for a small project:

Compute the expected activity completion times and the variance for each activity. If necessary, round your answer to two decimal places.

Most

Expected

Activity

Optimistic

Probable

Pessimistic

Times

Variance

A

4

5

6

B

8

9

10

C

7

7.5

11

D

7

9

10

E

6

7

9

F

5

6

7

An analyst determined that the critical path consists of activities B–D–F. Compute the expected project completion time and the variance. If necessary, round your answer to two decimal places.

Expected project completion time: .

Variance of projection completion time: .

Most

Expected

Activity

Optimistic

Probable

Pessimistic

Times

Variance

A

4

5

6

B

8

9

10

C

7

7.5

11

D

7

9

10

E

6

7

9

F

5

6

7

Explanation / Answer

Expected time (t)=1/6 (optimistic time + 4×most probable time+pessimistic time)

variance=((pessimistic time-optimistic time)/6)²

For activity A , Expected time=1/6 (4+4×5+6)=30/6=5

variance = ((6-4)/6)²=(1/3)² =0.11

For activity B , Expected time = 1/6 (8+4×9+10)=54/6=9

Variance = ((10-8)/6)²=(1/3)²=0.11

For activity C, Expected time = 48/6 =8

Variance = (2/3)²= 0.44

For activity D , Expected time= 53/6=8.83

Variance= (3/6)²=0.25

for activity E, Expected time = 43/6=7.17

Variance = (3/6)²=0.25

for activity F, Expected time= 36/6=6

Variance = (2/6)²=0.11

Critical path consists B-D- F. So,it has maximum project completion time and variance.

Expected project completion time = 9+8.83+6=23.83

Variance = 0.11+0.25+0.11=0.47

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote