Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Finer Furniture produces three types of wooden furniture – benches, tables, and

ID: 3121588 • Letter: F

Question

Finer Furniture produces three types of wooden furniture – benches, tables, and chairs. The production of each of these involves both a carpentry process and a finishing process. The time required in each of these as well as lumber requirements for each product are given below. For example, it takes 3 carpentry hours, 2 finishing hours, and 10 feet of lumber to produce one bench. The profit per unit is also given in the table.

The company wishes to get the maximum profit possible, and a linear program was developed for this purpose. The variables were defined as:

B = number of benches produced each month

T = number of tables produced each month

C = number of chairs produced each month

The linear program is:

Maximize Profit = 30B + 60T + 50C

Subject to:

       3B + 6T + 5C < 1800

       2B + 5T + 4C < 1200

10B + 30T + 15C < 5400

     B, T, C > 0

a. Suppose the company produced 60 benches, 60 tables, and 80 chairs. Find the total profit and the amount of each resource used. Put your answers on the answer sheet.

b. Find the optimal solution, and put the answers in the table on the answer sheet.

Benches Tables Chairs Amount available per month Carpentry hours 3 hr. 6 hr. 5 hr. 1800 Finishing hours 2 hr. 5 hr. 4 hr. 1200 Lumber (Feet) 10 ft. 30 ft. 15 ft. 5400 Profit $30 $60 $50

Explanation / Answer

a. Given that Profit = 30B+60T+50C

Therefore, total profit from 60 benches, 60 tables and 80 chairs = 30*60+60*60+50*80

= 1800 + 3600+4000

= 9400

To produce one bench it requires 3hrs for carpentry work, 2 hrs for finishing work and 10 ft of Lumber.

Therefore to produce 60 benches, Carpentry hours required = 60* 3 = 180 hours

   ,, Finishing hours required = 60*2 = 120 hours

,, Lumber requirement = 60*10 = 600 ft.   

To produce 60 tables, Carpentry hours required = 60* 6 = 360 hours

   ,, Finishing hours required = 60*5 = 300 hours

,, Lumber requirement = 60*30 = 1800 ft.

To produce 80 chairs, Carpentry hours required = 60* 5 = 300 hours

   ,, Finishing hours required = 60*4= 240 hours

,, Lumber requirement = 60*15 = 900 ft.

Therefore, Total Carpentry hours required = 180 + 360 + 300 = 840 hours

   ,, Finishing hours required = 120 +300 + 240 = 660 hours

,, Lumber requirement = 600 +1800 +900 = 3300 ft.

b.

The standard form of the LPP is

    Max Z = 30B + 60 T+ 50C

s.t.

   3B + 6T + 5C + S1 = 1800

    2B + 5T + 4C + S2 = 1200

    10B + 30T + 15 C + S3 = 5400

    B, T, C, S1, S2, S3 >= 0.

Table 1

Cj

30

60

50

0

0

0

Basis

Cb

Xb

B

T

C

S1

S2

S3

MINIMUM RATIO

S1

0

1800

3

6

5

1

0

0

300

S2

0

1200

2

5

4

0

1

0

240

S3

0

5400

10

30

15

0

0

1

180

Zj - Cj

-30

-60

-50

0

0

0

                                       Key column

Not all Zj – Cj values are >= 0. Hence the solution is not optimum. Hence go to next step

Table 2

Cj

30

60

50

0

0

0

Basis

Cb

Xb

B

T

C

S1

S2

S3

MINIMUM RATIO

S1

0

720

1

0

2

1

0

-5

360

S2

0

300

1/3

0

3/2

0

1

-1/6

200

T

60

180

1/3

1

½

0

0

1/30

360

Zj - Cj

-10

0

-20

0

0

2

Again solution is not optimum since some of the Zj-Cj values are negative. Hence the next table.

Table 3

Cj

30

60

50

0

0

0

Basis

Cb

Xb

B

T

C

S1

S2

S3

MINIMUM RATIO

S1

0

320

-3

0

0

1

-4/3

1/45

C

50

200

2

0

1

0

2/3

-1/9

T

60

80

-2/3

1

0

0

-1/3

4/45

Zj - Cj

60

60

50

0

40/3

14/9

In table 3, All Zj- Cj values are >=0.

Hence the solution is optimum.

The solution is

No. of Benches produced each month = 0

No. of Tables produced each month = 80

No. of chairs produced each month = 200

And the Maximum profit = 30 * 0 + 60 * 80 + 50 * 200 = 0+ 4800 + 10000 = 14800

Cj

30

60

50

0

0

0

Basis

Cb

Xb

B

T

C

S1

S2

S3

MINIMUM RATIO

S1

0

1800

3

6

5

1

0

0

300

S2

0

1200

2

5

4

0

1

0

240

S3

0

5400

10

30

0

15

0

0

1

180

Zj - Cj

-30

-60

-50

0

0

0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote