Which of the following manufacturing strategy has the shortest lead-time in gene
ID: 3132492 • Letter: W
Question
Which of the following manufacturing strategy has the shortest lead-time in general?
Select one:
A. Make-to-order
B. Engineer-to-order
C. Make-to-stock
D. Assemble-to-order
E. None of them
If there are customer orders the projected available after time fence is based on:
Select one:
A. Forecast demand
B. Customer orders
C. The greater of forecast demand and customer orders
D. The smaller of forecast demand and customer orders
E. None of them
Given the following data, (Week, Forecast): (1, 30), (2, 40), (3, 40), and (4, 30). There are 40 on hand. The lot size is 60. The MPS should be determined as needed (no shortage, no excessive inventory). Then the projected available balance at week 2 is:
Select one:
A. 50
B. 40
C. 30
D.
20
20
E. None of them
A work center was available for work 80 hours. it produced 65 standard hours of work and actually worked 70 hours. What is the performance of the work center?
Select one:
A. 107.7%
B. 92.9%
C. 87.5%
D. 90.0%
E. None of them
Explanation / Answer
Which of the following manufacturing strategy has the shortest lead-time in general?
B. Engineer-to-order
If there are customer orders the projected available after time fence is based on:
Select one:
A. Forecast demand
Given the following data, (Week, Forecast): (1, 30), (2, 40), (3, 40), and (4, 30). There are 40 on hand. The lot size is 60. The MPS should be determined as needed (no shortage, no excessive inventory). Then the projected available balance at week 2 is:
Select one:
B. 40
A work center was available for work 80 hours. it produced 65 standard hours of work and actually worked 70 hours. What is the performance of the work center?
Select one:
B. 92.9%
65 / 70 = 0.929 = 92.9%