QUES TION 5 Refer to the example in slides starting slide #55 for chapter 5 Create and upload a line of balance chart for end of pen d ll over her. Attach File Browse My Computer Browce Content Colletion QUESTION6 Which of the following methods will measure the cost efficiency of the work accomplished to date? OEV/AC EV/PV D AC/CV ACISV 1 poists Save Refer to question # 15 (page 121) in your textbook Assuming that the rating scale was changed to 1 3 and 5 (instead of 1 2 and 3 W is QUESTION 7 upsed air..tp

Explanation / Answer

The Cost Performance Index helps you analyze the efficiency of the cost utilized by the project.

"The Cost Performance Index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost"

Hence , EV/AC is the right answer.