part a.) probability of delay in the construction = (M)*(~L)*(~W) + (~M)*(L)*(~W) + (~M)*(~L)*(W) {since mutually exclusive }
= 0.4*0.6*0.8 + 0.6*0.4*0.8 + 0.6*0.6*0.2 = 0.192 + 0.192 + 0.072 = 0.456
part b.) probability of bad weather = 1 / (2+2+1) = 1/5 = 0.2