A factory supervisor is concerned that the time it takes workers to complete an

ID: 3160372 • Letter: A

Question

A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is to erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below.


She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds, respectively.


Referring to Table 17-4, suppose the sample mean and range data were based on 6 observations per hour instead of 5. How would this change affect the lower and upper control limits of an R chart?

LCL would increase; UCL would decrease.

LCL would remain the same; UCL would decrease.

Both LCL and UCL would remain the same.

LCL would decrease; UCL would increase.

LCL would increase; UCL would decrease.

LCL would remain the same; UCL would decrease.

Both LCL and UCL would remain the same.

LCL would decrease; UCL would increase.

Explanation / Answer

LCL would remain the same; UCL would decrease.

as it all cases LCL for R chart is 0. and as sample size increses ( from 5 to 6) the UCL decreses . this is property of sample that is we increses the sample size UCL will close to mean

LCL would remain the same; UCL would decrease.