1. For control chart, the lower and upper control limits are usually set at: fiv

ID: 3181466 • Letter: 1

Question

1. For control chart, the lower and upper control limits are usually set at:

five standard deviations from the centerline

four standard deviations from the centerline

three standard deviations from the centerline

two standard deviations from the centerline

e.

one standard deviation from the centerline

2.A company would like their process to have a capability index (Cp) which is:

less than 0.50

less than 1.00

greater than 1.00

equal to that of its competitors

none of the above

a.

five standard deviations from the centerline

b.

four standard deviations from the centerline

c.

three standard deviations from the centerline

d.

two standard deviations from the centerline

e.

one standard deviation from the centerline

Explanation / Answer

1)

three standard deviations from the centerline

option C is correct

2)

greater than 1.00

c.

three standard deviations from the centerline

option C is correct

2)

c.

greater than 1.00