you are estimating the install hours for an electronics upgrade based on the number of components affected. The upgrade for which you are estimating affects 36 components. Given the following equation, select the correct response from each pair.

Install Hours = 2.65 + 2.15 (# Components)

The independent variable is # Components

The independent variable is Install Hours

The slope is 2.15

The slope is 2.60

The estimated install hours for your upgrade is 80.00 hours

The estimated install hours for your upgrade is 95.75 hours

Explanation / Answer

The independent variable is # Components

The slope is 2.15

The estimated install hours for your upgrade is 80.00 hours