The Business School at Eastern College is collecting data as a first step in the
ID: 3204652 • Letter: T
Question
The Business School at Eastern College is collecting data as a first step in the preparation of next year's budget. One cost that is being looked at closely is administrative staff as a function of student credit hours. Data on administrative costs and credit hours for the most recent 13 months follow:
The controller's office has analyzed the data and given you the results from the regression analysis:
SUMMARY OUTPUT
ANOVA
Required:
a. In the standard regression equation y = a + bx, the letter b is best described as the:
b. In the standard regression equation y = a + bx, the letter y is best described as the:
c. In the standard regression equation y = a + bx, the letter x is best described as the:
d. If the controller uses the high-low method to estimate costs, the cost equation for administrative costs is: (Do not round your intermediate calculations.)
e. Based on the results of the controller's regression analysis, the estimate of administrative costs in a month with 1,010 credit hours would be: (Round your intermediate calculations to 2 decimals.)
f. The correlation coefficient (rounded) for the regression equation for administrative costs is:
g. The percent of the total variance (rounded) that can be explained by the regression is:
Explanation / Answer
Solution:-
a) In the standard regression equation y = a + bx, the letter b is best described as the Variable cost coefficient.
b) In the standard regression equation y = a + bx, the letter y is best described as the Dependent variable.
c) In the standard regression equation y = a + bx, the letter x is best described as the Independent variable.
d) Some other equation.
High low method to determine slope.
Step 1: Select the activity with the highest and lowest amounts. Choose 49,000 and 79,000 miles (March and April).
Step 2: Select the hour adjacent to those activities: $85,478 and $258,278. Note that the chours adjacent to these activity levels will be used, even though these cost amounts are not the highest and lowest 'costs.' A1317, 125
Step 3: Determine the slope (the variable cost per unit):
[$258,278 - $85,478]/[1317 - 125] = $ 144.97