e April 17 April 23 Chapter 12 Homework manager is simulating the number of time
ID: 3224722 • Letter: E
Question
e April 17 April 23 Chapter 12 Homework manager is simulating the number of times a machine operator stops a machine to make adjustments. After careful study the manager found that the number of stops ranged from one to five per cycle and that each number of stops was equally likely using the random numbers 0.1835 and 0.3094 that orden, the next two simulated cycles would respectively have stops for adjustment of Select one: a. 2 and 2. b. 1 and 2. c. 2 and 1 d. 1 and 1 e, 2 and 3. Next page You are logged in as Jayson Hinkle (Log out MGTExplanation / Answer
Question 1:
Option (c) is correct choice.
2 and 1.
Question 2:
Option (e) is correct choice.
A and B only.
That means, A description of the components of the system and a simulation clock.
Question 3:
Option (b) is correct choice.
Increase the number of replications.
Question 5:
Option (e) is correct choice.
All the above.
Question 6:
Option (c) is correct choice.
Many situations are too complex for mathematic solutions.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.