The proprietor of Midland Construction Company has to decide between two project
ID: 3245932 • Letter: T
Question
The proprietor of Midland Construction Company has to decide between two projects. He estimates that the first project will yield a profit of $170,000 with a probability of 0.6 or a profit of $150,000 with a probability of 0.4; the second project will yield a profit of $230,000 with a probability of 0.6 or a profit of $70,000 with a probability of 0.4. Find the expected profit for each project.
first project $
second project $
Which project should the proprietor choose if he wants to maximize his expected profit?
first project
second project
Explanation / Answer
First project:
x p xp
170,000 0.6 102,000
150,000 0.4 60,000
Expected profit of first project = 162,000
Second project:
x p xp
230,000 0.6 138,000
70,000 0.4 28,000
Expected profit of second project = 166,000
Since the expected profit of second project is more, proprietor should choose second project.
Thus, the answers to the questions asked are:
(a) fist project: 162,000
(b) econd project: 166,000
(c) Correct option: second project