Complete the following chart to determine which supplier will you choose accordi
ID: 325612 • Letter: C
Question
Complete the following chart to determine which supplier will you choose according to given scoring system and what are your selections's point of strengths and weaknesses?
Given the following background information:
Matching with project planning (10%)
Weight
Supplier 1
Supplier 2
Supplier 3
Supplier 4
Variance between project due date and proposed due date (days)
100%
34.00
46.00
46.00
42.00
Worst variance
46.00
Best variance
34.00
Technical proposal (40%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
Adherence to system design included in the proposal
50%
95%
87%
75%
90%
Historical supplier capability to adhere to design included in the proposal
35%
90%
77%
70%
70%
Effectiveness of communication of technical details
15%
40%
30%
20%
35%
Reorder lead time (5%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
Supplier lead time
100%
30
40
40
40
Average lead time
37.5
Variance with average lead time
-7.5
2.5
2.5
2.5
Worst variance
2.5
Best variance
-7.5
Supplier past performance (10%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
order freezing time
20%
0%
90%
50%
60%
payment terms
20%
100%
100%
100%
100%
delivery lead time
20%
100%
100%
100%
100%
open work in progress activities
20%
100%
100%
100%
100%
defects part per million
20%
100%
93%
12%
100%
Quotation for the project (10%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
Supplier quotation
100%
4900
9000
7250
6100
Average quotation
6812.5
Variance with average quotation
-1912.5
2187.5
437.5
-712.5
Worst variance
2187.5
Best variance
-1912.5
Quotation for future projects (15%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
Supplier quotation
100%
15150
27000
21550
21200
Average quotation
21225
Variance with average quotation
-6075
5775
325
-25
Worst variance
5775
Best variance
-6075
Quotation for repairing and maintenance (5%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
Supplier quotation
100%
38
40
40
35
Average quotation
38.25
Variance with average quotation
-0.25
1.75
1.75
-3.25
Worst variance
1.75
Best variance
-3.25
Supplier dependence rate (5%)
Weight
Supplier1
Supplier2
Supplier3
Supplier4
Supplier dependence rate
100%
0.16
0.66
0.42
0.01
Each sub-item has the following meaning:
• Technical proposal: evaluation of three items 1. Adherence to system design included in the proposal (50%) 2. Historical supplier capability to adhere to design included in the proposal (35%) 3. Effectiveness of communication of technical details (15%)
• Matching with project planning: for each supplier, the difference between the project due date and the proposed due date is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)]
• Reorder lead time: each supplier offers a lead time value, from which the average lead time is calculated; so, for each supplier, the difference between the average lead time and the proposed lead time is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)]
• Supplier past performance: ongoing suppliers are evaluated against four performance dimensions (order freezing time, payment terms, delivery lead time, open work in progress activities, defects part per million); for each, a threshold value is set (e.g. for defects part per million, it is 1%): each supplier receives a score between 0% and 100% according to how much the target value has been achieved (it is default 0% if the supplier has no performance data available). Each performance has the same weight (20%)
• Quotation for the project: each supplier offers a price for this project, from which the average price is calculated; so, for each supplier, the difference between the average price and the proposed price is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)];
• Quotation for future projects: each supplier offers a price for at three future project, from which the average price is calculated; so, for each supplier, the difference between the average price and the proposed price is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)];
• Quotation for repairing and maintenance: each supplier offers a price for maintenance and repair, from which the average price is calculated; so, for each supplier, the difference between the average price and the proposed price is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)];
• Supplier dependence: each supplier receives a score which equal the value of supplier dependence.
Pesi Supplier 1 Supplier 2 Supplier 3 Supplier 4 Technical area (65%) Technical proposal 40% 30% Matching with project planning 10% 70% Reorder lead time 5% 20% Supplier past performance (if applicable) 10% 10% Economic area (35%) Quotation for the project 10% 50% Quotation for future projects 15% 100% Quotation for repairing and maintenance 5% 100% Supplier dependence rate 5% 100% Total score 100% 51% Top supplier to be selected NOExplanation / Answer
Pesi Supplier 1 Supplier 2 Supplier 3 Supplier 4 Technical area (65%) Technical proposal 40% 85% 75% 65% 75% • Technical proposal: evaluation of three items 1. Adherence to system design included in the proposal (50%) 2. Historical supplier capability to adhere to design included in the proposal (35%) 3. Effectiveness of communication of technical details (15%) Matching with project planning 10% 100% 0% 0% 33% • Matching with project planning: for each supplier, the difference between the project due date and the proposed due date is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)] Reorder lead time 5% 100% 0% 0% 0% • Reorder lead time: each supplier offers a lead time value, from which the average lead time is calculated; so, for each supplier, the difference between the average lead time and the proposed lead time is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)] Supplier past performance (if applicable) 10% 80% 97% 72% 92% • Supplier past performance: ongoing suppliers are evaluated against four performance dimensions (order freezing time, payment terms, delivery lead time, open work in progress activities, defects part per million); for each, a threshold value is set (e.g. for defects part per million, it is 1%): each supplier receives a score between 0% and 100% according to how much the target value has been achieved (it is default 0% if the supplier has no performance data available). Each performance has the same weight (20%) Economic area (35%) Quotation for the project 10% 100% 0% 43% 71% • Quotation for the project: each supplier offers a price for this project, from which the average price is calculated; so, for each supplier, the difference between the average price and the proposed price is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)]; Quotation for future projects 15% 100% 0% 46% 49% • Quotation for future projects: each supplier offers a price for at three future project, from which the average price is calculated; so, for each supplier, the difference between the average price and the proposed price is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)]; Quotation for repairing and maintenance 5% 40% 0% 0% 100% • Quotation for repairing and maintenance: each supplier offers a price for maintenance and repair, from which the average price is calculated; so, for each supplier, the difference between the average price and the proposed price is calculated. Then, each supplier receives a score between 0 and 100% calculated as 1 – [(supplier variance – best variance)/(worst variance – best variance)]; Supplier dependence rate 5% 16% 66% 42% 1% • Supplier dependence: each supplier receives a score which equal the value of supplier dependence. Total score 100% 85% 43% 47% 62% Top supplier to be selected Yes No No No Given the following background information: Matching with project planning (10%) Weight Supplier 1 Supplier 2 Supplier 3 Supplier 4 Variance between project due date and proposed due date (days) 100% 34 46 46 42 Worst variance 46 Best variance 34 Technical proposal (40%) Weight Supplier1 Supplier2 Supplier3 Supplier4 Adherence to system design included in the proposal 50% 95% 87% 75% 90% Historical supplier capability to adhere to design included in the proposal 35% 90% 77% 70% 70% Effectiveness of communication of technical details 15% 40% 30% 20% 35% Reorder lead time (5%) Weight Supplier1 Supplier2 Supplier3 Supplier4 Supplier lead time 100% 30 40 40 40 Average lead time 37.5 Variance with average lead time -7.5 2.5 2.5 2.5 Worst variance 2.5 Best variance -7.5 Supplier past performance (10%) Weight Supplier1 Supplier2 Supplier3 Supplier4 order freezing time 20% 0% 90% 50% 60% payment terms 20% 100% 100% 100% 100% delivery lead time 20% 100% 100% 100% 100% open work in progress activities 20% 100% 100% 100% 100% defects part per million 20% 100% 93% 12% 100% Quotation for the project (10%) Weight Supplier1 Supplier2 Supplier3 Supplier4 Supplier quotation 100% 4900 9000 7250 6100 Average quotation 6812.5 Variance with average quotation -1912.5 2187.5 437.5 -712.5 Worst variance 2187.5 Best variance -1912.5 Quotation for future projects (15%) Weight Supplier1 Supplier2 Supplier3 Supplier4 Supplier quotation 100% 15150 27000 21550 21200 Average quotation 21225 Variance with average quotation -6075 5775 325 -25 Worst variance 5775 Best variance -6075 Quotation for repairing and maintenance (5%) Weight Supplier1 Supplier2 Supplier3 Supplier4 Supplier quotation 100% 38 40 40 35 Average quotation 38.25 Variance with average quotation -0.25 1.75 1.75 -3.25 Worst variance 1.75 Best variance -3.25 Supplier dependence rate (5%) Weight Supplier1 Supplier2 Supplier3 Supplier4 Supplier dependence rate 100% 0.16 0.66 0.42 0.01