Assume you are sequencing jobs using Johnson\'s rule. There are three jobs calle
ID: 326090 • Letter: A
Question
Assume you are sequencing jobs using Johnson's rule. There are three jobs called A, B and C. The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint. Job B requires 7 hours to assemble and 2 hours to paint. Job C requires 4 hours to assemble and 1 hour to paint. The objective is to minimize the total processing time of all jobs, using Johnson’s rule. What is the correct sequence to process the jobs?
A) A - C - B
B) B - C - A
C) B - A - C
D) A - B - C
E) C – B - A
Explanation / Answer
Time spent by 3 jobs at both steps are given below :
Step 1 ( Tine )
Step 2 ( Time )
Johnson’s Rule is:
The shortest processing time is 1 and that is in Step 2 for Job C . Therefore Job C to be done last.
The next shortest possible time is 2 and that is in step 2 for Job B . Therefore Job B to be done second last
Hence , the job to be done first is A
The correct sequence therefore is A-B-C
ANSWER : D ) A-B-C
Step 1 ( Tine )
Step 2 ( Time )
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.