Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

just need answer to last part Development of Version 2.0 of a particular account

ID: 3272458 • Letter: J

Question

just need answer to last part

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:

  

Activity

Normal Time (weeks)

Crash Time (weeks)

Normal Cost

Total Cost with Crashing

Immediate Predecessor(s)

A

44

33

$2,100

$2,700

long dash—

B

22

11

$2,300

$2,900

long dash—

C

33

33

$750

$750

long dash—

D

88

44

$2,300

$2,600

A

E

66

33

$900

$1,275

B

F

33

22

$3,200

$4,700

C

G

44

22

$1,400

$1,800

D, E

a) Based on the given information regarding the activities for the project, the project length =

16

weeks.

b) The total cost required for completing this project on normal time =

$12950.

c) For reducing the duration of the project by one week, the activity that should be crashed first is activity

D

.

The cost of the project based on the first activity selected for crashing will increase by

$75.

d) The maximum weeks by which the project can be reduced by crashing =

7

weeks.

Total cost of crashing the project to minimum (or maximum weeks possible) = ? $

Activity

Normal Time (weeks)

Crash Time (weeks)

Normal Cost

Total Cost with Crashing

Immediate Predecessor(s)

A

44

33

$2,100

$2,700

long dash—

B

22

11

$2,300

$2,900

long dash—

C

33

33

$750

$750

long dash—

D

88

44

$2,300

$2,600

A

E

66

33

$900

$1,275

B

F

33

22

$3,200

$4,700

C

G

44

22

$1,400

$1,800

D, E

Explanation / Answer

Total Cost crashing the project to minimum (or maximum week possible is $ 12300.