Hello, I need help with completing the following \" Earned Value Management (EVM

ID: 327694 • Letter: H

Question

Hello, I need help with completing the following "Earned Value Management (EVM) Fence problem." I have already completed most of the assignmnet, I just need some help with figuring the "RP", "AC" AND the "ETC-TIME", if applicable. You will need to input the calculations, answers, and the interpretations of all "RP", "AC" and the "ETC-TIME".

If there isn't a "ETC-TIME" applicable, you do not have to input that, but only if there isn't one. By any chance there is, please input that as well. Just go by how I completed everything within the pictures I insert here. Also, please check my answers to see if I completed everything properly, if I did not, please input the correct answers accordingly. Below, I will insert what I have so far, and the answers that I need help with. I will insert the exercise and a "reference/cheat sheet" for you to go by.

If answered correctly, points and possitive feedback will be given to you. Thank you so much for your assistance. Cheers!

_____________________________________________________________

EXERCISE :

---------------------

REFERENCE/CHEAT SHEET :

The Fence You have a project to build a new fence. The yard is square, the fence is four-sided of equal length and height. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day 3. Activity Day 1 Day 2 Day 3Day4Status End of Day 3 Complete, spent $1,000 Complete, Spent $1,200 50% done, spent $600 PF-F Side 2 Side 3 ideA S=Actual Start PS---S--PF PSPF Not yet started PF=Planned Finish F=Actual Finish PS=Planned Start , , ,

Explanation / Answer

What is Calculation answer RP 62.5/75*100 83.33% AC $1000+$1200+$600 $2800 ETC-Time 4/0.83 4.82 days