You are a subcontractor who won a contract to perform work on a project in Ohio.
ID: 327884 • Letter: Y
Question
You are a subcontractor who won a contract to perform work on a project in Ohio. You started work on Day=0 but did not file a Notice of Furnishing until Day=60. You ultimately worked a total of 90 continuous days on the project. It’s been 40 days since your last day of work on the project, and the GC has yet to pay you for any of this work—all your invoices are overdue. You have lien rights on the value of work provided on which days?
A Days 0-21
B Days 0-39
C Days 39-60
D Days 39-90
E None of the above.
Explanation / Answer
E. None of the above.
Reason: Since i have forgotten to file a notice of furnishing until day =60.I donot have lien rights to claim money for the work done till then. hence the answer is none of the above.