For this assignment, create a Project Schedule, and list the 20+ activities requ

ID: 327897 • Letter: F

Question

For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months

Unit 4 Project:

For this assignment, create a Project Schedule, and list the 20+ activities required to complete the house that you identified in your Unit IV Project Budget. Assign a schedule to all identified activities. Please be sure to reserve two weeks for contingencies. In other words, you should schedule all the activities and set aside two weeks for contingencies. The entire project (including the two-week contingency period) should equal 24 months

Unit 4 Project:

Activity Description Est $ Architectural Design 50,000 Procurement of machinery 60,000 Hiring Labor 120,000 Interior Design 15,000 Windows and Doors 20,000 HVAC 40,000 Framing 130,000 Lumber 80,000 Drywall 45,000 Interior Decorator and Decorations 20,000 Work and Environmental Permits 25,000 Landscaping 30,000 Scaffolding Rental 25,000 Paint and Wood Finishing 40,000 Plumbing 30,000 Electrical 30,000 Lighting Fixtures 20,000 Site Security 20,000 Roofing 40,000 Flooring 30,000 Exterior Rock 50,000 Plumbing Fixtures 20,000 Cabinetry 40,000 Concrete 80,000 Material Storage 10,000 Cost of Construction 1,070,000 Contingency (2%) 20,400 Total 1,090,400

Explanation / Answer

Total

Below is the PROJECT SCHEDULE

Project Start Date-1-05-2018

Project End Date-30-4-2018

The overall time of completion (24 months) includes the contingency time (2 weeks) as well

Activity Description Start Date End Date Days to complete Est $ Architectural Design 01-05-2018 15-05-2018 14 50,000 Procurement of machinery 15-05-2018 30-05-2018 15 60,000 Hiring Labor 31-05-2018 10-06-2018 10 1,20,000 Interior Design 11-06-2018 26-07-2018 45 15,000 Windows and Doors 25-07-2018 23-09-2018 60 20,000 HVAC 20-09-2018 30-10-2018 40 40,000 Framing 31-10-2018 28-02-2019 120 1,30,000 Lumber 10-02-2019 12-03-2019 30 80,000 Drywall 15-03-2019 29-04-2019 45 45,000 Interior Decorator and Decorations 30-04-2019 29-07-2019 90 20,000 Work and Environmental Permits 16-05-2018 26-05-2018 10 25,000 Landscaping 20-05-2018 27-05-2018 7 30,000 Scaffolding Rental 30-07-2019 06-08-2019 7 25,000 Paint and Wood Finishing 06-08-2019 20-10-2019 75 40,000 Plumbing 15-10-2019 14-11-2019 30 30,000 Electrical 10-11-2019 10-12-2019 30 30,000 Lighting Fixtures 01-12-2019 16-12-2019 15 20,000 Site Security 15-12-2019 25-12-2019 10 20,000 Roofing 26-12-2019 09-02-2020 45 40,000 Flooring 10-02-2020 25-02-2020 15 30,000 Exterior Rock 05-02-2020 20-02-2020 15 50,000 Plumbing Fixtures 20-02-2020 27-02-2020 7 20,000 Cabinetry 25-02-2020 06-03-2020 10 40,000 Concrete 05-03-2020 20-03-2020 15 80,000 Material Storage 21-03-2020 15-04-2020 25 10,000 Cost of Construction 10,70,000 Contingency (2%) 16-04-2020 30-04-2020 14 20,400

Total

Below is the PROJECT SCHEDULE

Project Start Date-1-05-2018

Project End Date-30-4-2018

The overall time of completion (24 months) includes the contingency time (2 weeks) as well

10,90,400