Q1. In continuous processes, bottlenecks are shifting frequently. True Or False

ID: 327975 • Letter: Q

Question

Q1. In continuous processes, bottlenecks are shifting frequently. True Or False

Q2. Cycle time is characteristic of a system while throughput time is associated with a particular job. True or False

Q3. In services, materials, labor, and capital inputs are used to create finished products. True or False

Q4. Workers in line flow production processes are often paid piece rate. True or False

Q5. The sum of the times required to complete the work for each task is referred to as the: a. Run time b. Cycle time c. Setup time d. Processing time e. Throughput time

Explanation / Answer

1. False. Bottleneck is fixed, inventory may get accumulated at different places.

2. False. Cycle time is connected to the job, but throughput time is connected system.

3. True. The create the final service.

4. False. It is dependent on their nature of work, payroll etc.

5. e. Throughput time