Create a cost estimate and model for building a new, state-of-the-art multimedia

ID: 330137 • Letter: C

Question

Create a cost estimate and model for building a new, state-of-the-art multimedia classroom for your organization within the next six months. The classroom should include 20 high-end personal computers with appropriate software for your organization, a network server, Internet access for all machines, an instructor station, and a projection system. Be sure to include personnel costs associated with the project management for this project. Document the assumptions you made in preparing the estimate and provide explanations for key numbers.

Explanation / Answer

This assignment is mainly focused on developing the cost estimation model for establishing a state of the art multimedia classroom in just six months. He different features which will be included in the classroom are20 high-end personal computers having the appropriate software, projection system, an instructor station, internet access for all machines and a network server. The data for the construction of the building is also provided and this is mainly focused on to break down the figures into different parts of a cost estimation plan.

Once this is accomplished, the estimation of the total cost will be done in order to facilitate the funds required for the creation of such a classroom. With the help of given data, estimation of the cost is done so that the developer is able to create a financial viability of developing the building. The estimation of the cost will help in determining whether the developer can initiate the construction or not.

Estimated development cost

Estimated development cost

Activity

Personnel

Duration

Cost

Site purchase cost

Owner/Company

2 months

160000

Construction

Planning costs

Planning

Project Manager

1 month

30000

Designing Cost

Designing

Architect

1 month

10000

Average floor building cost

Building

Contractor

2 weeks

(1125 x 4200)

25000

Instructor station

Building

Contractor

1 week

10000

Classroom Section

Contractor

1 week

10000

Installations

Personal computers

Installation

System Administrator

1 week

20000

Network Servers

Installation

System Administrator

1 week

15000

Projection System

Installation

System Administrator

1 week

10000

Internet Installation

Installation

System Administrator

1 week

10000

Total development costs

300000

Estimated development cost

Activity

Personnel

Duration

Cost

Site purchase cost

Owner/Company

2 months

160000

Construction

Planning costs

Planning

Project Manager

1 month

30000

Designing Cost

Designing

Architect

1 month

10000

Average floor building cost

Building

Contractor

2 weeks

(1125 x 4200)

25000

Instructor station

Building

Contractor

1 week

10000

Classroom Section

Contractor

1 week

10000

Installations

Personal computers

Installation

System Administrator

1 week

20000

Network Servers

Installation

System Administrator

1 week

15000

Projection System

Installation

System Administrator

1 week

10000

Internet Installation

Installation

System Administrator

1 week

10000

Total development costs

300000