Average of 2,000 charts need to be coded each month. If it takes an average of 1
ID: 3303842 • Letter: A
Question
Average of 2,000 charts need to be coded each month. If it takes an average of 15 minutes to code each chart - how many charts does the average coder code per 8hours day? - how many charts does the average coder per 40hours week - how many charts does the average coder working 1 day per month? Average of 2,000 charts need to be coded each month. If it takes an average of 15 minutes to code each chart - how many charts does the average coder code per 8hours day? - how many charts does the average coder per 40hours week - how many charts does the average coder working 1 day per month? - how many charts does the average coder code per 8hours day? - how many charts does the average coder per 40hours week - how many charts does the average coder working 1 day per month?Explanation / Answer
Here, given is 2000 charts per month means 30 days and it takes 15 minute to each chart it means total time for 2000 chart = 30000
a) let x chart does the code per 8 hour day
8 hour means 8*60 minute = 480 minute
2000 : 30000 = x : 480
x = 480 * 2000 /30000
x = 32
So, 32 charts does the average coder code per 8hour day
b) Let x charts does code per 40 hour week
40 hour means 40*60 = 2400 minute
2000 : 30000 = x: 2400
x = 2400 * 2000 / 30000
x = 160
160 charts does the average coder code per 40 hour week
c) 2000 charts in monyh means in 30 days
2000 : 30 = x : 1
x = 2000/30
x = 66.67 charts