*THE BLACKED OUT SECTION IS THE PREVIOUS QUESTION. THIS IS BLACKED OUT SO THAT Y

ID: 331313 • Letter: #

Question

*THE BLACKED OUT SECTION IS THE PREVIOUS QUESTION. THIS IS BLACKED OUT SO THAT YOU ANSWER THE QUESTION WHICH IS SHOWN*

MS Project Problem - Suppose we have a complete activity predecessor table (shown below). Using MS Project, enter the activities, their durations and predecessors (use default Fixed Units). Submit the MS t Plan based on the activities below to the appropriate Dropbox (10 pts.). Activ Activity Description Duration Predecessors Conduct competitive analysis Review field sales reports Conduct tech capabilities assessment Develop focus group data Conduct telephone surveys Identify relevant specification improwements Interface with marketing staff Develop engineering specifications Check and debug designs Develop testing protocol Identify critical performance levels Assess and modify product components Conduct capabilities assessment ?, ? 12 selection criteria Develop RFQ (Request for Quote) Develop Collaborate with sales staff duction master schedule N, O are product launch 8. If Activity B, Review field sales reports, takes 7 days to complete instead of the 2 days estimated, what happens to the total Duration and why? A) Total Duration does not change because slack not totally used up B) Total Duration does not change because only used up slack that was available Assign8 Exec Eval C) Total Duration increases by 2 days, because used up 3 days of slack plus 2 additional days D) Total Duration increases by 2 days, because of critical path change, slack not overused

Explanation / Answer

8) The answer is B. Critical path is longest path and B is longer than C by 2 days in 2nd case.

Activity D cannot start till A, B and C are complete. After completion of activity A, B & C activity would simultaneously start. However, in 1st case B would complete in 2 days and C took 5 days. To begin activity D, there was a 3-day wait after B got over. However, there will be now a 2-day wait after C completes as B will push out timeline by 2-days.