Question

Connect " Course Materials-2181-1-22 × ? D AltCat 21.1 BOM-KEY.pdf X Y e Chegg Study Guided Soluti r × ? e chegg Study l Guided Solutio/X ? CSecure https://newconnect.mheducation.com/flow/connect.html HW7 - Chapter 21 Help Save & Exit Submit my work 2 Problem 21-10 In the following MRP planning schedule for ltem J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank be certain to enter "O" wherever required.) WEEK NUMBER ITEN J Gross requirements On-hand Net requiresents Planned order receipt Planned order release 0341:02 70 49 69 35 Sklpped Hint: enter "O" for "Scheduled receipts Hint Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases 70 49 69 Pre 2 of 3 Next >

Explanation / Answer

Item J , Lead time = 1 , Q = L4L

Period 1

Period 2

Period 3

Period 4

Period 5

Gross requirement

0

70

0

49

69

Scheduled receipts

0

0

0

0

0

Projected available balance

35

0

0

0

0

Net requirement

0

35

0

49

69

Planned order receipt

0

35

0

49

69

Planned order release

35

0

49

69

0

Item J , Lead time = 1 , Q = L4L

Period 1

Period 2

Period 3

Period 4

Period 5

Gross requirement

0

70

0

49

69

Scheduled receipts

0

0

0

0

0

Projected available balance

35

0

0

0

0

Net requirement

0

35

0

49

69

Planned order receipt

0

35

0

49

69

Planned order release

35

0

49

69

0