The overall average on a process you are attempting to monitor is 50.0 units. Th
ID: 3327361 • Letter: T
Question
The overall average on a process you are attempting to monitor is 50.0 units. The process population standard deviation is 1.72. Sample size is given to be 16. a) Determine the 3-sigma x-chart control limits. Upper Control Limit (UCunits (round your response to two decimal places) Lower Control Limit (LCLunits (round your response to two decimal places). b) Now determine the 2-sigma x Upper Control Limit (UC )-units (round your response to two decimal places) Lower Control Limit (LCL^)-units (round your response to two decimal places) How do the control limits change? 0 A. The control limits are tighter for the 2-sigma x-chart than for the 3-sigma x-chart. O B. The control limits are tighter for the 3-sigma x chart than for the 2 sigma x chart. O C. The control limits for the 2-sigma x-chart and for the 3-sigma x-chart are the same.Explanation / Answer
a) UCL = mean + k*s/sqrt(n)
LCL = mean - k*s/sqrt(n)
here mean = 50 , k = 3 , s = 1.72 , n = 16
using the formula given above
we get
UCL = 51.29
LCL = 48.71
b) here k= 2
UCL = 50.86
LCL = 49.14
c) control limit for 2- sigma is tighter
option A) is correct
Please rate
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.