The following is a table of activities associated with a project at Rafay Ishfaq

ID: 333780 • Letter: T

Question

The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede Activity Duration (weeks) Precedes A (start) F (end) This exercise contains only parts b, c, and d b) The activities on the critical path are A-C-F c) The total project completion time for Rafay Ishfaq's software firm is 14 weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks)

Explanation / Answer

As A, C and F are the activities on the critical path, the slack times for each of these activities = 0 weeks.

This is because we cannot delay any of these activities as they are on critical path.

Other paths include -

ABEF = 1+1+9+2 = 13 weeks.

Hence, the activity B can be delayed by maximum 1 week which will make ABEF 14 weeks which is equal to current critical path.

Activitu E can also be delayed by maximum 1 week hich will make ABEF 14 weeks which is equal to current critical path.