This one is a little harder, but think it through. Your project has been experie
ID: 3348995 • Letter: T
Question
This one is a little harder, but think it through. Your project has been experiencing delays so far, based on a lack of available human resources for a critical piece of work which resulted from a labor dispute. After months of negotiations, the labor dispute has finally been resolved and you will have ready access to the resources you need moving forward. In this context, which formula would you use to determine what the project will likely have spent in total upon completion? 0 A) EAC = BAC/CPI 0 B) EAC=AC + Bottom-up ETC O c) EAC = AC + (BAC-EV) D) EAC = (BAC-EV) / (BAC-AC)Explanation / Answer
As per condition given above, initially due to labour cricis, cost estimated initially was impacted but after resolving labour issue continuation in project is expected. Therefore formula for EAC will be,
EAC=AC+(BAC-EV). Hence option (c) is correct.
Note- please find me in comment box if you find any difficulty.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.