Problem 1. Eighty units of end item E are needed at the beginning of week 6 and
ID: 336820 • Letter: P
Question
Problem 1. Eighty units of end item E are needed at the beginning of week 6 and lead-time for E is 2 weeks. Tern cases (30 units per case) of J have been ordered and are scheduled to arrive (receive) in week 1. Note: J must be ordered by the case, B must be produced in multiples of 120 units, and F must be ordered in multiples of 200. There are 60 units of B and 20 units of J now on hand, and there is no inventory of F. Lead times are two weeks each for E and B, one week for J, and one week for F. Prepare a material requirements plan for all components. B(2 (3) (4) FI2)Explanation / Answer
Problem 1. Eighty units of end item E are needed at the beginning of week 6 and lead-time for E is 2 weeks. Tern cases (30 units per case) of J have been ordered and are scheduled to arrive (receive) in week 1. Note: J must be ordered by the case, B must be produced in multiples of 120 units, and F must be ordered in multiples of 200. There are 60 units of B and 20 units of J now on hand, and there is no inventory of F. Lead times are two weeks each for E and B, one week for J, and one week for F. Prepare a material requirements plan for all components. B(2 (3) (4) FI2)
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.