Two efficiency indicators that reflect the cost and schedule performance of a pr
ID: 337350 • Letter: T
Question
Two efficiency indicators that reflect the cost and schedule performance of a project are:
a. Cost projection index (CPI) and schedule projection index (SPI)
Actual cost (AC) and Planned value (PV)
c. Cost performance index (CPI) and Schedule performance index (SPI)
d. Cost pricing index (CPI) and schedule performance index (SPI)
a. Cost projection index (CPI) and schedule projection index (SPI)
b.Actual cost (AC) and Planned value (PV)
c. Cost performance index (CPI) and Schedule performance index (SPI)
d. Cost pricing index (CPI) and schedule performance index (SPI)
Explanation / Answer
Two efficiency indicators that reflect the cost and schedule performance of a project are:
a. Cost projection index (CPI) and schedule projection index (SPI)
Actual cost (AC) and Planned value (PV)
c. Cost performance index (CPI) and Schedule performance index (SPI)
d. Cost pricing index (CPI) and schedule performance index (SPI)
a. Cost projection index (CPI) and schedule projection index (SPI)
b.Actual cost (AC) and Planned value (PV)
c. Cost performance index (CPI) and Schedule performance index (SPI)
d. Cost pricing index (CPI) and schedule performance index (SPI)