Answers only Please don’t make it confusing Please be clear Please write or type neatly A pro ect has four activities A, B, C and D that must be performed sequentially. The probability distributions for the i me required to complete each of the activities are os Activity Time (weeks) Activity Probability 0.34 0.33 0.29 0.04 0.22 10 0.5 0.26 0.07 0.20 0.37 0.16 0.20 0.72 0.28 13 15 17 19
Explanation / Answer
a. Base case using most likely completion times.
Worst Case using last activity time for each
Best Case using first activity time for each
b.
c. Simulation provide a distribution of project completion time values. The 37 weeks or less of times weeks and under can be used to estiamte the probability that the project will be completed within weeks.
Activity Base Case(weeks) Worst Case(weeks) Best Case (weeks) A 8 11 8 B 5 7 3 C 15 19 11 D 6 8 6 Total 34 45 28Related Questions