Assume the following data was given for the set-up time and run time for CNC Dri
ID: 3382059 • Letter: A
Question
Assume the following data was given for the set-up time and run time for CNC Drill and Manual Drill.
Set-up Time (per order)
Run Time (per board)
CNC Drill
300
1
Manual Drill
30
16
Which of the following statements is/are true?
I. Choose the CNC drill for order (batch) sizes greater than 18
II. Choose the manual drill for order (batch) sizes greater than 18
III. Choose the CNC drill for order (batch) sizes less than 18
IV. You can choose either CNC drill or manual drill for order (batch) sizes equal to 18
Please include forumla used.
Set-up Time (per order)
Run Time (per board)
CNC Drill
300
1
Manual Drill
30
16
Explanation / Answer
IV. You can choose either CNC drill or manual drill for order (batch) sizes equal to 18