Problem 2 (40 Points) : Shown below are the PERT schedule and the precedence rel
ID: 3394793 • Letter: P
Question
Problem 2 (40 Points): Shown below are the PERT schedule and the precedence relationships among the activities required to complete a project.
1-Setup the project activity network diagram for the following relationships in the table and determine the critical path.
2-What is the probability if the company wants the project completed in more than 32 weeks?
Activity
Optimistic Time (weeks)
Mode
Time (weeks)
Pessimistic
Time (weeks)
Preceding Activities
A
2
3
5
-
B
3
4
6
A
C
6
8
11
B
D
5
6
9
A
E
6
8
10
D
F
4
5
6
D
G
5
6
9
F
H
2
3
4
C, E
I
1
3
5
C, E, G
J
4
5
8
H, I
K
2
3
5
J
L
5
9
11
C, E, G
Activity
Optimistic Time (weeks)
Mode
Time (weeks)
Pessimistic
Time (weeks)
Preceding Activities
A
2
3
5
-
B
3
4
6
A
C
6
8
11
B
D
5
6
9
A
E
6
8
10
D
F
4
5
6
D
G
5
6
9
F
H
2
3
4
C, E
I
1
3
5
C, E, G
J
4
5
8
H, I
K
2
3
5
J
L
5
9
11
C, E, G
Shown below air the PERT schedule and the precedence relationship among the activities required to complete a project. Setup the project activity network diagram for the following realationships in the table and determine the critical path. What is the probability id the company wants the project complete in more than 32 weeks?Explanation / Answer
Problem 2 (40 Points) : Shown below are the PERT schedule and the precedence rel
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.