Consider a process consisting of five resources that are operated eight hours pe
ID: 340457 • Letter: C
Question
Consider a process consisting of five resources that are operated eight hours per day. The process works on three different products, A, B, and C Processing Processing time for A time for B Number Processing time for C Resource workers (minutes) (minutes) (minutes) 2 3 4 5 4 15 4 3 4 Demand for the three different products is as follows: product A, 40 units per day; product B, 50 units per day; and product C, 60 units per day a. What is the bottleneck? Resource 1 Resource 2 Resource 3 Resource 4 Resource 5 What is the flow rate for Flow A assuming that demand must be served in the mix C)? What is the flow rate for Flow B assuming that demand must be served in the mix C)? What is the flow rate for Flow C assuming that demand must be served in the mix C)? b. described above (i.e., for every four units of A, there are five units of B and six units of units per day c. described above (i.e., for every four units of A, there are five units of B and six units of units per day d. described above (i.e., for every four units of A, there are five units of B and six units of units per dayExplanation / Answer
A.
If assumed each user individualy works the bottleneck is Resource 3
.
But if they are minimum required (And there is no parallel activity for multiple users) then Bottleneck is Resource 5.
Units 40 50 60 Resource No of workers Time A Time B Time C 1 2 5 5 5 2 2 4 4 5 3 1 15 0 0 4 1 0 3 3 5 2 6 6 4 Time required Total time Per user 2 200 250 300 750 375 2 160 200 300 660 330 1 600 0 0 600 600 Bottleneck 1 0 150 180 330 330 2 240 300 240 780 390Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.